HC Morgan WPCF Clarifier Weir, Baffle and Skimmer Arm Replacement
Bailey-Alexander Complex
1501 W Samford Ave
-
(334) 501-3060 -
webwtrswr@auburnalabama.org -
- M-F
- 7:30AM-4:30PM
-
\t\t\t\t{{SocialMediaLinks}} \t\t\t \t\t
Project Overview Sewer System Improvements
This project consists of replacing the existing fiberglass reinforced plastic (FRP) weirs and baffles as well as the existing painted steel skimmer arms on Clarifiers 1 and 2 at the H.C. Morgan WPCF. The project will involve replacing the existing FRP weirs and baffles with stainless steel weirs and baffles that are not subjected to warping or corrosion.
The project was completed on Oct 31, 2024 with a total capital budget of $206,880.28.
Photos
Timeline
Nov 2024
Close Out Finishes
Nov 30, 2024
Nov 2024
Close Out Starts
Nov 1, 2024
Oct 2024
Construction Finishes
Oct 31, 2024
Jan 2024
Construction Starts
Jan 22, 2024
Dec 2023
Contracts Finishes
Dec 1, 2023
Oct 2023
City Council Starts
Oct 3, 2023
Oct 2023
Contracts Starts
Oct 3, 2023
Oct 2022
Bid Opening Starts
Oct 6, 2022
Oct 2022
Bid Advertisement Finishes
Oct 6, 2022
Sep 2022
Bid Advertisement Starts
Sep 8, 2022
Sep 2022
Design Finishes
Sep 1, 2022
May 2022
Design Starts
May 6, 2022